Measure the forms, choose an allowance and compare delivery volume with bag counts.
How to Use
Quick answer: A 10 ft × 10 ft slab that is 4 in thick takes about 1.358 cubic yards with 10% extra. Using nominal yields of 0.45 and 0.60 cubic feet, that is 82 bags of 60 lb mix or 62 bags of 80 lb mix.
Choose the shape that matches the space inside your forms. For a rectangular slab, enter length, width and thickness. For a round column, enter inside diameter and filled height. For a continuous strip footing of uniform cross section, enter run length, width and depth. Measure each dimension perpendicular to the other two. If your forms step down or an edge gets thicker, break the project into pieces and calculate those volumes separately.
Use the feet and inches boxes together. For ten feet four inches enter 10 in Feet and 4 in Inches. For a four-inch slab enter 0 feet and 4 inches for thickness. In metric mode the corresponding boxes represent meters and centimeters. Changing the unit converts the displayed dimensions. Measure the formed space itself and check that the units on your tape match the labels on the screen.
Consider a patio measuring 10 feet by 10 feet with a uniform four-inch depth. The unadjusted volume is 100 × 4/12, or 33⅓ cubic feet. With the default 10% allowance, the estimate is 36⅔ cubic feet, about 1.3580 cubic yards or 1.0383 cubic meters. At the nominal yields below, this is 82 bags of 60 lb mix or 62 bags of 80 lb mix. These are alternative orders for the same pour.
For the same patio with the allowance set to 0%, the estimate is 1.235 cubic yards, 75 bags of 60 lb mix or 56 bags of 80 lb mix. With 10% extra, it is 1.358 cubic yards, 82 bags or 62 bags, respectively. If you compare bagged mix with a ready-mix quote, give the supplier the cubic yardage, dimensions and allowance. The 82 smaller bags weigh 4,920 lb dry and the 62 larger bags weigh 4,960 lb dry, before any water is added.
The Formula Behind It
Slab or strip footing: volume = length × width × depth. Round column: volume = π × (diameter ÷ 2)² × height.
Convert all three measurements to the same unit before multiplying. One yard is three feet long, so a cubic yard contains 3 × 3 × 3 = 27 cubic feet. One cubic foot equals 0.028316846592 cubic meters. The tool calculates the base volume, multiplies by one plus the waste percentage divided by 100, then converts the adjusted volume into the three displayed units.
An allowance accounts for variation in the excavated base, small spills and material left on equipment. Ten percent is the starting setting. A supplier familiar with your project can suggest an allowance and order increment. If you include an allowance here and your supplier adds another one independently, the order can end up larger than you expected. Share both your measured dimensions and your selected percentage.
Recommended Slab Thickness
These are estimating examples for common applications. They describe depths you can enter when comparing quantities. Final thickness depends on loads, foundation conditions, drainage, reinforcement, local requirements and project specifications. Confirm the designed section before ordering. A small change in depth is significant across a large area.
| Application | Example depth | Planning detail |
|---|---|---|
| Pedestrian sidewalk | 4 inches | Use the specified depth along the full run |
| Patio slab on grade | 4 inches | Measure thickened edges separately |
| Residential driveway example | 6 inches | Confirm vehicle loads and base design |
| Strip footing | Use the plan depth | Measure the actual trench or form width |
A 20-foot by 20-foot placement gains about 33⅓ cubic feet for every extra inch of average thickness. Measure low spots before relying on a single depth. For an L-shaped patio, draw a line that divides it into two rectangles with no overlap. Add their volumes, keeping the same units throughout. A shared edge has no volume, but counting a shared area twice can materially inflate the result.
How Many Bags Do You Need?
Nominal yields used here are 0.45 cubic feet for a 60 lb bag and 0.60 cubic feet for an 80 lb bag. Divide the adjusted volume in cubic feet by the applicable yield, then round up to the next whole bag. Product families and formulations vary. Read the yield printed on the exact mix you plan to purchase. QUIKRETE Concrete Mix product information.
| Finished depth | 60 lb bag coverage | 80 lb bag coverage |
|---|---|---|
| 3 inches | 1.80 sq ft | 2.40 sq ft |
| 4 inches | 1.35 sq ft | 1.80 sq ft |
| 6 inches | 0.90 sq ft | 1.20 sq ft |
The coverage entries assume uniform thickness and contain no additional waste. To estimate coverage at another depth, divide the bag yield in cubic feet by thickness in feet. For example, a depth of six inches is half a foot, so an 80 lb bag covers 0.60 ÷ 0.5 = 1.20 square feet.
Frequently Asked Questions
Does the result already include waste?
Yes. All three volume outputs and both bag counts include the percentage shown in the waste field. Set it to zero to see the geometric volume, then restore your chosen allowance before sharing the estimate with a supplier.
Should I order the 60 lb and 80 lb quantities together?
Each figure independently covers the full estimate. Choose one bag size, or work out a mixed purchase by multiplying each bag count by its labeled yield and checking that their combined volume covers the adjusted requirement.
Should I measure the radius or the diameter?
Enter the diameter measured straight across the inside of the round form through its center. The tool halves that dimension before squaring it. Entering a radius in the diameter field reduces the calculated column volume to one quarter.
How do I estimate a footing with corners?
Measure runs so the volumes meet without overlapping. Working from a dimensioned plan, divide the footprint into separate rectangles. Calculate each run with its own width and depth if they vary, and combine the results before rounding bags.
How do I calculate several matching columns?
Calculate one column and multiply its unrounded volume by the number of matching columns. Apply your allowance once and round bags at the end. Multiplying the single-column bag count can overstate the total because each individual quantity was rounded up.
Can I use this for a slab with a slope?
A slab with parallel top and bottom surfaces has a uniform thickness. For a simple wedge over a level rectangle, an average of the end depths may be appropriate. Split irregular grades into measured sections or use the quantities on your drawings.
Why does a supplier quote a different number of yards?
Suppliers may round to dispatch increments, apply minimum loads or use measured site conditions different from yours. Compare the base volume, allowance and order increment separately. A quoted delivery quantity can exceed the volume inside the completed forms.
Can this calculator choose reinforcement or footing depth?
It estimates material volume for dimensions you supply. Use the project plans or local professional responsible for the design to determine load capacity, reinforcement and footing geometry. Enter those dimensions once the structural decisions have been made.